Public Private Partnership (PPP)
|
|
Location :
|
Near GSFC Junction on Mumbai Delhi Railway Line near Vadodara
|
Concessionaire :
|
Ranjit Projects Pvt. Ltd. Mehsana
|
Project Cost :
|
Rs. 2706.30 lakhs
|
Length of Bridge :
|
1032 m
|
Width of Carriage Way :
|
2 x 7.5m(Dual carriageway) having 1.2 m median & 1.5 m Footpath on either side.
|
Month / Year of construction completion:
|
March 2003
|
Concession Period :
|
181 Months (Including construction period).
|
|
Concessionaire :
|
|
MSK Project Pvt. Ltd. Baroda
|
Project Cost :
|
|
Rs. 7 crore
|
Length :
|
|
8.7 Km
|
Width of Carriage Way :
|
|
7.0 m
|
Paved shoulders on Both sides having equivalent crust same as the main carriageway
:
|
|
1.5 m
|
Hard side shoulder on both sides :
|
|
1.0 m
|
Design Speed :
|
|
80 Km/Hour
|
Month / Year of construction completion:
|
|
April 2006
|
Concession Period:
|
|
15 years
|
|
Concessionaire :
|
|
M. S. Khurana Infrastructure and Toll Road Private Limited. Ahmedabad
|
Project Cost :
|
|
Rs.35.04 Cr
|
Length :
|
|
45 Kms
|
Width of Carriage Way :
|
|
7.0 m
|
Paved shoulders on Both sides having equivalent crust same as the main carriageway
:
|
|
1.5 m
|
Hard side shoulder on both sides :
|
|
1.0 m
|
Month / Year of construction completion:
|
|
February 2008
|
Concession Period:
|
|
13 years 3 months 2 days
|
Number of Toll Sections:
|
|
Two
|
|
Concessionaire :
|
|
M/s MSK Projects (Kim-Mandvi Corridor) Pvt Ltd. Vadodara
|
Project Cost :
|
|
Rs. 21.10 Crore
|
Length :
|
|
45 Kms
|
Width of Carriage Way :
|
|
7.0 m
|
Paved shoulders on Both sides having equivalent crust same as the main carriageway
:
|
|
1.5 m
|
Hard side shoulder on both sides :
|
|
1.0 m
|
Month / Year of construction completion:
|
|
August 2010
|
Concession Period:
|
|
20 Years
|
Number of Toll Sections:
|
|
Two
|
|
Concessionaire :
|
|
M/s Ranjit Toll Road Pvt Ltd.
|
Project Cost :
|
|
Rs. 47 Crore
|
Length :
|
|
44.12 Kms
|
Width of Carriage Way :
|
|
7.0 m
|
Paved shoulders on Both sides having equivalent crust same as the main carriageway
:
|
|
1.5 m
|
Hard side shoulder on both sides :
|
|
1.0 m
|
Month / Year of construction completion:
|
|
March 2011
|
Concession Period:
|
|
28 Years
|
Number of Toll Sections:
|
|
Two
|
|
Concessionaire :
|
|
L&T Rajkot-Vadindar Tollway Ltd.
|
Project Cost :
|
|
Rs.774.80 Cr
|
Length :
|
|
131.65 Kms
|
Width of Carriage Way :
|
|
4 lane divided dual Carriageway with median.
|
Paved shoulders on Both sides having equivalent crust same as the main carriageway
:
|
|
1.5 m
|
Hard side shoulder on both sides :
|
|
1.0 m
|
Month / Year of construction completion:
|
|
February 2012
|
Concession Period:
|
|
20 years
|
Number of Toll Sections:
|
|
Three
|
|
Concessionaire :
|
|
L&T Halol – Shmalaji Tollway Ltd.
|
Project Cost :
|
|
Rs.808.65 Cr
|
Length :
|
|
173.03 Kms
|
Width of Carriage Way :
|
|
4 lane divided dual Carriageway with median.
|
Paved shoulders on Both sides having equivalent crust same as the main carriageway
:
|
|
1.5 m
|
Hard side shoulder on both sides :
|
|
1.0 m
|
Month / Year of construction completion:
|
|
April 2012
|
Concession Period :
|
|
20 years
|
Number of Toll Sections :
|
|
Four
|
|
Concessionaire :
|
|
L&T Ahmedabad – Maliya Tollway Ltd.
|
Project Cost :
|
|
Rs.1015.36 Cr
|
Length :
|
|
180.05 Kms
|
Width of Carriage Way :
|
|
4 lane divided dual Carriageway with median.
|
Paved shoulders on Both sides having equivalent crust same as the main carriageway
:
|
|
1.5 m
|
Hard side shoulder on both sides :
|
|
1.0 m
|
Month / Year of completion :
|
|
Sec - III - April 2012 Sec IV - May 2012 Sec - I - Sept 2012 Sec - II - Nov 2012
|
Concession Period :
|
|
22 years
|
Number of Toll Sections :
|
|
Four
|
|